Client: Transport Malta

Supervisor: EMDP Ltd.

This project was started in December 2005 and completed slightly ahead of schedule in December 2006. The project consisted in the re construction of Hal far road from Lyster Barracks roundabout to the Freeport Terminal at Birzebbuga. The road alignment was improved and dangerous curves were eliminated. The project included a considerable amount of new mass masonry retaining walls cladded with rubble walls. New potable water mains, sewer mains, electrical cables and telecommunication duct routes were installed. A storm water pipe was also laid to collect storm water runoff.

Newsclips

11.12.2005 Reconstruction of Hal Far Road kicks off

17.12.2006 Hal Far road re-opened to traffic