Posted: August 20th, 2011 | Filed under: Curriculum Vitae, Projects | No Comments »

Valletta Road, Zurrieq
Brief Description
Client: Transport Malta
Supervisor: Edwin Mintoff & Associates
This project was started in January 2010 and had to be completed within 36 weeks.
The Valletta Road Zurrieq Reconstruction project consisted in the laying of new services such as sewer mains, potable water mains, 6 way duct routes for telecommunication cables, Enemalta cables and a storm water network. The road was completely rebuilt. It includes reinforced C30 concrete hard shoulders on both sides. Crash barriers and new street lighting were also installed. A reservoir was built for storm water harvesting.
The project was completed on budget and ahead of schedule.
Newsclips
05.02.2010 Valletta Road to be completed by August 2010
27.07.2010 Valletta Road re-opened to traffic within budget and ahead of schedule
29.07.2010 The Valletta Road Project is completed to high standards and ahead of schedule
Posted: August 20th, 2011 | Filed under: Curriculum Vitae, Projects | No Comments »

San Lawrenz Road
Brief Description
Client: Ministry for Gozo
Supervisor: iAS Ltd.
Works on the 3km long stretch from Victoria, next to the Pope John Paul II monument, to San Lawrenz was carried out in 2006. Works were successfully carried out by MACjv, a joint venture between Schembri Infrastructures Ltd, Bonnici Brothers Ltd and Road Construction Company Ltd.
This road forms part of arterial road 1 forming the backbone of the road network of Malta. It is used by visitors to Ta Pinu Sanctuary and to Dwejra. Water mains, sewer mains, electrical cables and telecommunication duct routes and a 1.8m high walk through service culvert were installed. Mass masonry walls were also built along the road.
Newsclips
19.3.2006 Ministers tour works on San Lawrenz road
03.09.2006 Extensive Road reconstruction Projects in Gozo
Posted: August 20th, 2011 | Filed under: Curriculum Vitae, Projects | No Comments »

Hal Far Road - Phase III
Brief description
Client: Transport Malta
Supervisor: EMDP Ltd.
This project was started in December 2005 and completed slightly ahead of schedule in December 2006. The project consisted in the re construction of Hal far road from Lyster Barracks roundabout to the Freeport Terminal at Birzebbuga. The road alignment was improved and dangerous curves were eliminated. The project included a considerable amount of new mass masonry retaining walls cladded with rubble walls. New potable water mains, sewer mains, electrical cables and telecommunication duct routes were installed. A storm water pipe was also laid to collect storm water runoff.
Newsclips
11.12.2005 Reconstruction of Hal Far Road kicks off
17.12.2006 Hal Far road re-opened to traffic